Air Quality Control Projects

Cinergy Solutions: Boiler MACT Study & Design
Location: Dual Options for Confidential Process Plant with Seven Coal-Fired Boilers in Virginia
Client: Cinergy Power Generation Services LLC
Description: 

Development and performance of an EPC Boiler Mact study and project at the site of a confidential process plant in Virginia.

Cholla Station
Location: Joseph City, Ariz.
Client: Arizona Public Service
Description: 

Engineer-procure-construct services for an emission control project at Cholla Station in Joseph City, Ariz., for Arizona Public Service.

Milton R. Young Units 1 & 2
Location: Center, N.D.
Client: Minnkota Power Cooperative
Description: 

Preliminary engineering, detailed design, field engineering support and startup services for air quality control retrofits in Grand Forks, N.D., for Minnkota Power Cooperative.

University of Missouri: Boiler MACT Phase I Study
Location: University of Missouri-Columbia Power Plant
Client: University of Missouri-Columbia
Description: 

Baseline emissions testing and results analysis for multiple Industrial Boiler MACT compliance options for the University of Missouri-Columbia.

Cooper Station Unit 2
Location: Somerset, Ky.
Client: East Kentucky Power Cooperative
Description: 

Preliminary engineering, detailed design, field engineering support, startup services and construction management for an air quality control system retrofit in Somerset, Ky., for East Kentucky Power Cooperative.

Confidential Industrial Client: Boiler MACT Study
Location: Coal-Fired Industrial Boiler Facility
Client: Confidential Industrial Client
Description: 

Identification and evaluation of the impacts of the proposed Industrial Boiler MACT rule on a coal-fired industrial boiler facility.

Purdue University: Boiler MACT Study
Location: West Lafayette, Ind.
Client: Wade Utility Plant, Purdue University
Description: 

Development and performance of a Boiler MACT study for the Wade Utility Plant in West Lafayette, Ind.

Louisa Generating Station
Location: Muscatine, Iowa
Client: MidAmerican Energy Co.
Description: 

Engineer-procure-construct services for an emission control retrofit at Louisa Generating Station in Muscatine, Iowa, for MidAmerican Energy. Included pulse-jet fabric filters, ash handling and a dry lime flue gas desulfurization (FGD) system.

Citizens Thermal Energy: Boiler MACT Compliance
Location: Perry K Steam Plant
Client: Citizens Thermal Energy
Description: 

Development of alternative strategies and capital cost estimates for the retrofit of air pollution control (APC) equipment at the Perry K Steam Plant in Indianapolis.

Youngdong Unit 2 FGD Retrofit
Location: Korea
Client: Korea Power Engineering Co. (KOPEC)
Description: 

Design support services for the installation of a proprietary flue gas desulfurization (FGD) process at a coal-fired power station in Korea.

Aventine Renewable Energy: Boiler MACT Study
Location: Pekin, Ill.
Client: Aventine Renewable Energy Inc.
Description: 

Engineering and design services for new air pollution control systems for two coal-fired stoker boilers to enable compliance with the Industrial Boiler MACT standards for Aventine Renewable Energy in Pekin, Ill.

Jeffrey Energy Center Units 1, 2 & 3 Upgrade Project
Location: St. Marys, Kan.
Client: Westar Energy
Description: 

Design and procurement for the upgrade of existing limestone wet flue gas desulfurization (WFGD) system to achieve in excess of 95 percent SO2 removal at Westar's Jeffrey Energy Center Units 1, 2 and 3 in St. Marys, Kan.

TXU Reliable Texas Planning Study
Location: Texas, Various
Client: TXU Power
Description: 

Professional services to study carbon capture and storage (CCS) options for eight supercritical pulverized coal reference plants proposed by TXU Power as part of its Reliable Texas Power Project.

Poryong Units 5-8 FGD Retrofits
Location: Korea
Client: Korea Power Engineering Co. (KOPEC)
Description: 

Engineering, field construction management, startup and testing for the construction of four new flue gas desulfurization (FGD) systems at a coal-fired generation station in Korea.

Walter Scott Jr. Energy Center Unit 3 FGD Retrofit
Location: Council Bluffs, Iowa
Client: MidAmerican Energy Co.
Description: 

Joint venture engineer-procure-construct (EPC) contracting services for a turnkey emission control retrofit project at the Walter Scott Jr. Energy Center in Council Bluffs, Iowa, including complete engineering, procurement, construction, startup and commissioning, for MidAmerican Energy Co.

Huntington Station Unit 2
Location: Huntington, Utah
Client: PacifiCorp
Description: 

A turnkey emission control project (conversion of electrostatic precipitator to pulse-jet fabric filter and a wet lime flue gas desulfurization retrofit) including complete engineering, procurement, construction, startup and commissioning for Huntington Station Unit #2.

Bunge: Boiler MACT & Particulate Control Study
Location: Five Plants in Illinois, Indiana and Ohio
Client: Bunge NA Inc.
Description: 

Development and performance of Phase I Boiler MACT (Maximum Achievable Control Technology) study for five plant facilities in Illinois, Indiana and Ohio for Bunge, identifying air pollution control modifications necessary for compliance.

Hercules: Boiler MACT & Particulate Control System Study
Location: Coal-Fired Industrial Facility
Client: Hercules Inc.
Description: 

Identification and evaluation of the impacts of the proposed Industrial Boiler MACT rule on a coal-fired industrial boiler facility for Hercules in Louisiana, Mo., studying four compliance alternatives for three coal-fired boilers and two steam turbines.

Voluntary Reporting of Greenhouse Gases
Client: Westar (formerly Western Resources)
Description: 

Greenhouse gas inventory and documented greenhouse gas reduction projects in accordance with the Energy Policy Act of 1992 for Westar, formerly Western Resources.

Cornell University: ICI Boiler MACT Phase I Study
Location: Boilers 1 and 8
Client: Cornell University, Ithaca, N.Y.
Description: 

Plan development for compliance with the Industrial Boiler MACT rule for Cornell University, Ithaca, N.Y., including compliance options, economic analysis and selection recommendations.

Corporate Environmental Responsibility Report & Greenhouse Gas Inventory
Location: Dallas
Client: AMR, parent company of American Airlines
Description: 

Preparation of a corporate environmental responsibility report in which a greenhouse gas inventory was a critical component for American Airlines.

Crystal River Units 4 & 5 AQCS Retrofit
Location: Crystal River, Fla.
Client: Progress Energy
Description: 

Engineer-procure-construct (EPC) joint venture contractor for a turnkey emission control project at Progress Energy's Crystal River Units 4 and 5, including complete engineering, procurement, construction, startup and commissioning.

Boswell Unit 3 AQCS Detailed Design
Location: Cohasset, Minn.
Client: Minnesota Power
Description: 

Detailed engineering, project management and startup assistance for an environmental retrofit at Minnesota Power’s second-largest coal facility, Boswell Unit 3, in Cohasset, Minn., including technology to achieve reductions in sulfur dioxide (SO2), nitrogen oxides (NOx), mercury (Hg) and particulate emissions.

Purdue University: Boiler MACT Compliance Design
Location: West Lafayette, Ind.
Client: Purdue University, Wade Utility Plant
Description: 

Engineering and design services for new air pollution control systems that will put Purdue's Wade Utility Plant boilers in compliance with Boiler MACT standards.

Wausau Paper: Boiler MACT & Particulate Control Study
Location: Coal-Fired, Industrial Boiler Facility
Client: Wausau Paper Co.
Description: 

Identification and evaluation of the impacts of the proposed Industrial Boiler MACT rule on a coal-fired industrial boiler facility for Wausau Paper in Rhinelander, Wis.