Delaware Mountain Collector Line
Location: Guadalupe Mountains National Park, Texas
Client: National Wind Power
Completion Date: 1999
This 9-mile 34.5-kV vertical collector line for 40 wind turbines) was built in hard-to-access terrain. The topography required the construction of many angle and dead-end structures. The challenging schedule required design, staking, material procurement and construction to be completed in approximately six months.
- Engineering design
- Procurement
- Construction