Burns & McDonnell has performed planning, design and construction phase services for the Dodge City Regional Airport since 1999. Projects completed during that tenure include:

  • Milling and overlays of runways and taxiways
  • Installation of new runway and taxiway lighting
  • Installation of precision approach path indicators (PAPIs) for Runway 2-20
  • Reconstruction of Taxiway B
  • Slurry sealing runways and taxiways
  • Reconstruction of taxiways and the main entrance road
  • A new aircraft rescue and fire fighting (ARFF) facility
  • Procurement of a new ARFF truck
  • Master plan update
  • Annual updates to the airport's capital improvement plan data sheets

Services

  • Planning, design and construction phase services
  • Mill and overlay Runway 2-20
  • Mill and overlay Runway 14-32
  • Mill and overlay Taxiway A and connecting taxiways
  • Install PAPIs on Runway 2-20
  • Reconstruct Taxiway B
  • Mill and overlay Taxiway A
  • Construct new ARFF building
  • Procurement of ARFF truck
  • Reconstruct entrance road
  • Slurry seal runways 2-20 and 14-32
  • Install MIRLs for runways 2-20 and 14-32
  • Install MITls for all airfield taxiways
  • Airport master plan