Market price shifts and extended equipment lead times created budget and schedule risks. The project was one of the first municipal projects in Oklahoma authorized under the Department of Environmental Quality’s flexible permitting process for progressive design-build, which allowed our team to release early design packages and prepurchase long-lead filter equipment ahead of cost increases. Close collaboration allowed ongoing scope adjustments to preserve the budget, including having the city self-perform some tasks.