We are the engineer-procure-construct (EPC) contractor for a 138-kV/34.5-kV substation and interconnecting 138-kV switchyard tying the 80-megawatt (MW) High Horizon solar power facility to the grid in West Virginia.
Opdenergy, a renewable power producer focused on solar and onshore wind production, elected to self-build the interconnection switchyard, which is within the FirstEnergy service territory and will be built to FirstEnergy specifications.
The substation has: four underground feeders to the photovoltaic (PV) solar facility; a single 138/34.5-kV power transformer; a 138-kV circuit breaker. It also has a prefabricated outdoor metal-clad switchgear distribution and control enclosure skid.
The switchyard includes: three 145-kV circuit breakers; six disconnect switches; and a prefabricated control building. The two yards are connected by a 138-kV slack span generation tie.