PROJECT

Wichita's Northwest Water Facility

Our team is leading the progressive design-build delivery of Wichita's Northwest Water Facility via a joint venture partnership with Alberici.

A progressive design-build approach allows us to facilitate collaboration among the city, designer and contractor at the earliest possible stages of the project to see that the design progresses with input from all project stakeholders. As the design evolves, our team can make design decisions within the context of the capital budget and life cycle cost, ultimately maximizing value.

In 2018, the team defined the requirements of a new 120-MGD facility and completed the preliminary design that had the ability to treat 100% groundwater, 100% surface water and any blend of the two independent sources to current and anticipated drinking water standards. This flexibility — to use any available water source at a given time —  provides much-needed drought resiliency to the City of Wichita.

The facility was designed to include the equivalent of 24 hours of water storage and a high-service pump station to facilitate water delivery directly to the existing and planned water distribution system. On-site underground electrical power and backup generators will provide the facility with sufficient power in the event the plant experiences a power outage or severe weather event. 

After a year of preliminary design, value engineering and process optimization, our team delivered the City of Wichita a $494 million cost proposal — $15 million below the city’s capital budget — with a projected $6 million per year in operational savings. Our team also helped the city complete its application for Water Infrastructure Finance and Innovation Act (WIFIA) funding through the U.S. Environmental Protection Agency (EPA). This facility is one of 38 water infrastructure capital projects the EPA is financing.

Client

City of Wichita

Location

Wichita, Kansas

Region

Midwest

Service

Water & Wastewater Program Management

Industry

Water

Project Profile

Want to learn more about this project?

Background

With an 80-plus-year-old water treatment facility and a growing population, the City of Wichita decided to construct a new facility to treat multiple water sources ranging from 100% groundwater to 100% surface water. Wichita's Northwest Water Facility allows the city to leverage its diverse water supply and operate in a flexible and sustainable manner based on climatic conditions.

The City of Wichita currently operates the Main Water Treatment Plant, which includes the Central Plant with a capacity of 130 million gallons per day (MGD) and the East Plant with a capacity of 30 MGD. Although the facility was partially rehabilitated and upgraded in 1992, the original plants are more than 80 years old and lack the necessary redundancies to provide resiliency and flexibility the city requires for a sustainable future.

With more than 550,000 residents to serve, the city set out to improve reliability. The process of rehabilitating the existing facility while maintaining treatment would be a costly project, so the city chose to construct a new facility. The site of Wichita's Northwest Water Facility was chosen due to its proximity to the convergence of pipelines from the city’s two primary water sources: the Equus Beds Aquifer (groundwater) and the Cheney Reservoir (surface water).

Burns & McDonnell has been working in partnership with the City of Wichita on its water treatment infrastructure since the 1990s. This long-standing relationship meant our team was deeply familiar with critical aspects of this project. 

Features

Wichita's Northwest Water Facility is the largest infrastructure project the City of Wichita has undertaken, which makes stakeholder engagement a major component of our work. This project affects ratepayers; therefore, our team is helping stakeholders understand the importance of the project and the phases of work with significant public outreach, education and stakeholder engagement.

The new water treatment facility will treat multiple sources including groundwater, aquifer storage, recovery sourced water and surface water through a single treatment plant with multiple treatment schemes. This gives the city flexibility to switch between water sources depending on climatic condition, achieving the city’s goal of developing a diverse and sustainable water supply that serves nearly 20% of Kansas’ population. It will also provide the city with appropriately sized operations, laboratory, maintenance and administration spaces.